CALL ORDER: 105 PROJECT NO.: HISP-5231(14) Lancaster County CONTRACTORS TOTAL COMMONWEALTH ELECTRIC CO $1,987,898.00 WATTS ELECTRIC COMPANY $2,501,879.65         CALL ORDER: 200 PROJECT NO.: STP-50-2(136) Sarpy County CONTRACTOR     TOTAL VRANA & SON CONSTRUCTION...

August 26, 2021

  CALL ORDER: 100 PROJECT NO.: HSIP-80-8(164) Lancaster & Seward Counties CONTRACTORS TOTAL CONSTRUCTORS, INC $17,411,486.05             CALL ORDER: 105 PROJECT NO.: NH-80-8(161) Lancaster & Seward Counties CONTRACTOR     TOTAL CONSTRUCTORS, INC $14,712,304.86...

July 22, 2021

CALL ORDER: 100 PROJECT NO.: NH-80-9(73) Cass County  CONTRACTORS TOTAL DIAMOND SURFACE INC 1,474,675.32 INTERSTATE SEALANT & CONCRETE INC. 1,530,384.60 IOWA CIVIL CONTRACTING INC. 1,838,296.78 SCODELLER CONSTRUCTION INC.   CALL ORDER: 200 PROJECT NO.: NH-6-7(183)...

June 17, 2021

CALL ORDER: 200 PROJECT NO.: ER-3490(13)  CONTRACTORS TOTAL M.E. CONTRACTING 514.415.60 SAWYER CONSTRUCTION CO. 316,827.70 VALLEY CORPORATION 385,562.22 CALL ORDER: 300 PROJECT NO.: STP-D3(107)  CONTRACTOR     TOTAL CONSTRUCTORS INC. 23,136,960.09 DIXON CONSTRUCTION...

May 6, 2021

CALL ORDER: 200 PROJECT NO.: NH-80-9(113) CONTRACTORS TOTAL HAWKINS CONSTRUCTION COMPANY 16,353,434.26 IOWA CIVIL CONTRACTING INC 13,987,892.65 CALL ORDER: 305 PROJECT NO.: S-275-6(1054) CONTRACTOR     TOTAL GRAHAM CONSTRUCTION INC 43,670,467.30 KOSS CONSTRUCTION CO...

April 8, 2021

CALL ORDER: 150 PROJECT NO.:MISC-D1(1038) CONTRACTORS TOTAL M.E. COLLINS CONTRACTING 983,500.00 MIDWEST INFRASTRUCTURE INC 609,500.00 VAN KIRK BROS CONTRACTING 645,500.00 CALL ORDER: 250 PROJECT NO.: MISC-D2(1051) CONTRACTOR     TOTAL M.E. COLLINS CONTRACTING...