CALL ORDER: 105
PROJECT NO.: M0001
MULTIPLE COUNTIES
| CONTRACTORS | TOTAL |
| DUSTROL, INC | 1,356,000.00 |
| MIDWEST COATINGS CO INC | |
| DON KEHN CONSTRUCTION | 2,652,500.00 |
CALL ORDER: 200
PROJECT NO.:SRR-89(32)
WASHINGTON COUNTY
| CONTRACTOR | TOTAL |
| M.E. COLLINS CONTRACTING CO, INC | |
| MIDWEST INFRASTURCTURE, INC | 493,778.69 |
| OMNI ENGINEERING (OLDCASTLE) | 294,967.15 |
CALL ORDER: 300
PROJECT NO.: NH-30-5(134)
PLATTE COUNTY
| CONTRACTOR | TOTAL |
| HAWKINS CONSTRUCTION COMPANY | 38,994,626.66 |
| PAULSEN, INC | 35,838,636.05 |
| REEDE CONSTRUCTION, INC | |
CALL ORDER: 310
PROJECT NO.: ER-3575(2)
DAKOTA & DIXON COUNTIES
| CONTRACTOR | TOTAL |
| DIXON CONSTRUCTION CO | 1,459,680.58 |
| HERBST CONSTRUCTION, INC | 1,499,872.25 |
| IOWA CIVIL CONTRACTING, INC | |
| MIDWEST INFRASTRUCTURE, INC | 1,428,077.25 |
| SIMON CONTRACTORS INC | 1,811,800.00 |
CALL ORDER: 400
PROJECT NO.: STP-281-1(119)
WEBSTER & ADAMS COUNTIES
| CONTRACTORS | TOTAL |
| VONTZ PAVING, INC | 14,106,153.35 |
| WERNER CONSTRUCTIONGS CO INC | 15,844,529.36 |
| WESTERN ENGINEERING CO INC | |
CALL ORDER: 500
PROJECT NO.:NH-20-1(148)
DAWES & SIOUX COUNTIES
| CONTRACTOR | TOTAL |
| WERNER CONSTRUCTION INC | 5,469,074.11 |
| WESTERN ENGINEERING CO INC | 5,541,752.10 |
CALL ORDER: 800
PROJECT NO.: ER-1787(5)
BROWN COUNTY
| CONTRACTOR | TOTAL |
| DIXON CONSTRUCTION CO | 2,122,910.75 |
| HERBST CONSTRUCTION, INC | |
| MIDWEST INFRASTRUCTURE, INC | 2,443,108.81 |
| SIMON CONTRACTORS INC | 2,498,000.00 |
| WERNER CONSTRUCTION LLC | |
CALL ORDER: 805
PROJECT NO.: ER-02300(2)
HOLT COUNTY
| CONTRACTOR | TOTAL |
| A&R CONSTRUCTION CO | 1,567,551.56 |
| BARNES CONSTRUCTION | |
| NORTH CONSTRUCTION LLC | 1,540,632.00 |
| WERNER CONSTRUCTION INC | |
CALL ORDER: 810
PROJECT NO.: STP-NH-7-4(122)
MULTIPLE COUNTIES
| CONTRACTOR | TOTAL |
| MISSOURI PETROLEUM PRODUCTS CO | 1,861,999.75 |
| STA-BILT CONSTRUCTION COMPANY | 1,887,367.00 |