CALL ORDER: 100
PROJECT NO.: NH-80-9(97)
Cass, Lancaster Counties
| CONTRACTOR | TOTAL |
| DYKHUIS DRILLING CORP | |
| GARCIA-CHICOINE ENTERPRISES | |
| INTERSTATE SEALANT & CONCRETE | 4,751,750.00 |
| IOWA CIVIL CONTRACTING | 4,288,818.49 |
| K2 REAL ESTATE DEVELOPMENT | |
| MIDWEST COATINGS | |
| SCODELLER CONSTRUCTION |
CALL ORDER: 105
PROJECT NO.: NH-80-9(98)
Sarpy, Cass Counties
| CONTRACTOR | TOTAL |
| DYKHUIS DRILLING CORP | |
| GARCIA-CHICOINE ENTERPRISES | |
| INTERSTATE SEALANT & CONCRETE | |
| IOWA CIVIL CONTRACTING | |
| K2 REAL ESTATE DEVELOPMENT | |
| MIDWEST COATINGS | |
| SCODELLER CONSTRUCTION | 6382,987.19 |
CALL ORDER: 110
PROJECT NO.:STP-15-2(127)
Butler County
| CONTRACTOR | TOTAL |
| CONSTRUCTORS INC | 5,122,327.05 |
| WERNER CONSTRUCTION | 4,950,024.62 |
| WESTERN ENGINEERING CO | 4,727,334.33 |
| PAVERS COMPANIES | |
| ,HENNINGSEN CONSTRUCTION |
CALL ORDER: 115
PROJECT NO.: BRM-7076(24)
Saline County
| CONTRACTOR | TOTAL |
| DIXON CONSTRUCTION | 1,593,807.75 |
| HERBST CONSTRUCTION | 1,482,536.95 |
| JJK CONSTRUCTION | 1,407,473.88 |
| K2 REAL ESTATE DEVELOPMENT | 1,290,904.65 |
| KEA CONSTRUCTORS | |
| MIDWEST INFRASTRUCTURE | 1,521,929.54 |
| SIMON CONTRACTORS |
CALL ORDER: 120
PROJECT NO.: STP-8-6(116)
Pawnee, Gage Counties
| CONTRACTOR | TOTAL |
| CONSTRUCTORS INC | 4,890,769.41 |
| PAVERS COMPANIES | |
| WERNER CONSTRUCTION | 4,809.518.70 |
| WESTERN ENGINEERING CO |
CALL ORDER: 200
PROJECT NO.: MAPA-28(120)
Douglas County
| CONTRACTOR | TOTAL |
| COMMONWEALTH ELECTRIC | 3,248,723.20 |
| SADLER ELECTRIC | 3,822,851.85 |
| WATTS ELECTRIC CO | 3,999,654.05 |
CALL ORDER: 300
PROJECT NO.:STP-9-4(118)
Dixon County
| CONTRACTOR | TOTAL |
| DIXON CONSTRUCTION | |
| HERBST CONSTRUCTION | |
| KNIFE RIVER MIDWEST | 10,999,202.87 |
| WERNER CONSTRUCTION | |
| WESTERN ENGINEERING |
CALL ORDER: 305
PROJECT NO.: NH-275-6(143)
Cuming County
| CONTRACTOR | TOTAL |
| A & R CONSTRUCTION CO | 2,081,146.03 |
| HARRIS CONSTRUCTION INC | |
| IOWA CIVIL CONTRACTING | |
| K2 REAL ESTATE DEVELOPMENT | 3,401,471,.50 |
| KIEWIT INFRASTRUCTURE CO | |
| ME COLLINS CONTRACTING | 2,633,179.75 |
| VAN KIRK SAND & GRAVEL |
CALL ORDER: 310
PROJECT NO.: STP-59-5(108)
Knox County
| CONTRACTOR | TOTAL |
| KNIFE RIVER MIDWEST | 3,553,722.28 |
| WERNER CONSTRUCTION | 3,425,253.92 |
| WESTERN ENGINEERING | 3,557,950.55 |
CALL ORDER: 315
PROJECT NO.:stp-75-3(123)
Washington, Burt Counties
| CONTRACTOR | TOTAL |
| CONSTRUCTORS INC | 4,699,901.16 |
| K2 REAL ESTATE DEVELOPMENT | |
| KNIFE RIVER MIDWEST | 5,381,945.80 |
| WERNER CONSTRUCTION | |
| WESTERN ENGINEERING | 4,502,680.02 |
CALL ORDER: 400
PROJECT NO.: NH-80-6(114)
Buffalo, Hall Counties
| CONTRACTOR | TOTAL |
| PAULSEN | |
| VONTZ PAVING | |
| WERNER CONSTRUCTION | 12,248,935.19 |
| WESTERN ENGINEERING |
CALL ORDER: 405
PROJECT NO.: NH-80-7(166)
Hamilton, York Counties
| CONTRACTOR | TOTAL |
| VONTZ PAVING | |
| WERNER CONSTRUCTION | 10,332,451.57 |
| WESTERN ENGINEERING |
CALL ORDER: 410
PROJECT NO.: HSIP-81-1(122)
Fillmore County
| CONTRACTOR | TOTAL |
| A & R CONSTRUCTION | |
| DIAMOND ENGINEERING | 475,061.16 |
| IOWA CIVIL CONTRACTING | |
| K2 REAL ESTATE DEVELOPMENT | 557,080.20 |
| ME COLLINS CONTRACTING | 381,623.32 |
| PAULSEN | 346,725.10 |
| VAN KIRK SAND & GRAVEL | 396,859.26 |
| WERNER CONSTRUCTION | 336,906.45 |
CALL ORDER: 415
PROJECT NO.: STP-74-5(114)
Fillmore County
| CONTRACTOR | TOTAL |
| CONSTRUCTORS INC | 1,639,137.35 |
| DIAMOND ENGINEERING | |
| IOWA CIVIL CONTRACTING | |
| K2 REAL ESTATE DEVELOPMENT | 2,490,601.60 |
| KIEWIT INFRASTRUCTURE | |
| ME COLLINS CONTRACTING | 2,297,261.96 |
| PAULSEN | 1,549,704.77 |
| WERNER CONSTRUCTION | 1,430,977.13 |
CALL ORDER: 510
PROJECT NO.: STP-L17J(107)
Cheyenne County
| CONTRACTOR | TOTAL |
| INTERSTATE HIGHWAY CONSTRUCTION | 13,742,019.84 |
| KOSS CONSTRUCTION | 13,985,947.09 |
| PAUL REED CONSTRUCTION & SUPPLY | |
| PAULSEN | 12,373,941.30 |
| SCOTT CONTRACTING INC | 15,000,000.00 |
| SIMON CONTRACTORS | |
| WERNER CONSTRUCTION | 14,641.821.64 |
CALL ORDER: 520
PROJECT NO.: STP-92-1(124)
Scotts Buff County
| CONTRACTOR | TOTAL |
| PAULSEN | 3,262,420.50 |
| SIMON CONTRACTORS | 3,148,700.00 |
| WERNER CONSTRUCTION | 3,068,458.11 |
| WESTERN ENGINEERING | 3,386,446.94 |
CALL ORDER: 600
PROJECT NO.: NH-80-4(151)
Lincoln County
| CONTRACTOR | TOTAL |
| HIGHWAY IMPROVEMENT INC | 360,140.00 |
| INTERSTATE SEALANT & CONCRETE | 348,250.00 |
| IOWA CIVIL CONTRACTING | |
| MIDWEST COATINGS INC | 233,600.00 |
| SCODELLER CONSTRUCTION | 315,060.00 |
CALL ORDER: 605 WITHDRAWN POSTPONED TO 9/3/20 LETTING
PROJECT NO.: NH-80-3(134)
Keith County
| CONTRACTOR | TOTAL |
CALL ORDER: 610
PROJECT NO.: NH-STP-80-3(152)
Keith County
| CONTRACTOR | TOTAL |
| C J MOYNA & SONS | |
| INTERSTATE HIGHWAY CONSTRUCTION | 49,775,118.56 |
| KOSS CONSTRUCTION | 46,880,859.38 |
CALL ORDER: 615
PROJECT NO.: STP-21-2(118)
Dawson County
| CONTRACTOR | TOTAL |
| PAULSEN | 4,354,807.45 |
| VONTZ PAVING | |
| WERNER CONSTRUCTION | |
| WESTERN ENGINEERING |
CALL ORDER: 800
PROJECT NO.: STP-183-4(117)
Rock County
| CONTRACTOR | TOTAL |
| MARTIN RESOURCE MANAGEMENT CORP DBA MONARCH OIL | 817,337.60 |
| STA-BILT CONSTRUCTION | 888,811.00 |
CALL ORDER: 805
PROJECT NO.: STP-61-4(116)
Cherry County
| CONTRACTOR | TOTAL |
| PAULSEN | 4,264,532.36 |
| VONTZ PAVING | |
| WERNER CONSTRUCTION | 3,367,524.23 |
| WESTERN ENGINEERING | 3,338,560.35 |
CALL ORDER: 810
PROJECT NO.: ER-2115(6)
Holt, Boyd County
| CONTRACTOR | TOTAL |
| A M COHRON & SON | 7,792,423.50 |
| DIAMOND ENGINEERING | |
| HAWKINS CONSTRUCTION | 10,421,362.84 |
| KEA CONSTRUCTORS | |
| KIEWIT INFRASTRUCTURE | 17,947,867.00 |
| SIMON CONTRACTORS | |
| UNITED CONTRACTORS | 6,619,741.95 |