January 24, 2019 – Letting

Nebraska Department of Roads Bid Letting

Below are the UNOFFICIAL bid results for the Nebraska Department of Roads bid letting on January 24, 2019. 

CALL ORDER: 150

PROJECT NO.:M10033
 District 1 Erosion Control – Various Counties

CONTRACTOR     TOTAL
BAB Inc 515,075
K2 Real Estate Development 398,390

CALL ORDER: 155

PROJECT NO.: M10034

District 1 Grading – Various Counties

CONTRACTOR     TOTAL
K2 Real Estate Development 550,000
M E Collins Contracting Company 472,570
Van Kirk Sand & Gravel 954,030

CALL ORDER: 250

PROJECT NO.: M20033
District 2 Erosion Control – Various Counties

CONTRACTOR     TOTAL
Bayshore Contractors
K2 Real Estate Development 457,088
Next Phase Environmental/Ryan W. Young 401,240

CALL ORDER: 255

PROJECT NO.: M20034 
District 2 Grading – Various Counties

CONTRACTOR     TOTAL
Bayshore Contractors
K2 Real Estate Development 658,905
ME Collins Contracting Company 562,000
Next Phase Environmental/Ryan W Young 611,923
Van Kirk Sand & Gravel
Valley Corp 1,186,518

CALL ORDER: 300

PROJECT NO.: STP-91-5(125)
Platte County

CONTRACTOR     TOTAL
Constructors Inc 5,919,711
Henningsen Const Inc 5,954,747
Knife River Corp / Knife River Midwest
Werner Construction 6,159,812
Western Engineering Company 5,593,669

CALL ORDER: 350

PROJECT NO.: M30033 
District 3 Erosion Control – Various Counties

CONTRACTOR     TOTAL
Next Phase Environmental/Ryan W Young 509,550

CALL ORDER: 355

PROJECT NO.:M30034
District 3 Grading – Various Counties

CONTRACTOR     TOTAL
M E Collins Contracting Company 439,460
Next Phase Environmental/Ryan W Young 603,575
Van Kirk Sand & Gravel

CALL ORDER:450 

PROJECT NO.: M40033
District 4 Erosion Control – Various Counties

CONTRACTOR     TOTAL
B A B Inc 463,737
Kirk Barnes Construction
Green Thumb

CALL ORDER: 455

PROJECT NO.: M40034
District 4 Grading – Various Counties

CONTRACTOR     TOTAL
Kirk Barnes Construction
Van Kirk Sand & Gravel 7,26,450

CALL ORDER: 550

PROJECT NO.: M50033
District 5 Erosion Control – Various Counties

CONTRACTOR     TOTAL
Kirk Barnes Construction 632,350
Paul Reed Construction & Supply
Gross Seed Company 367,625

CALL ORDER: 555

PROJECT NO.: M50034 
District 5 Grading – Various Counties

CONTRACTOR     TOTAL
Kirk Barnes Construction 662,250
Paul Reed Construction & Supply 425,880
Van Kirk Sand & Gravel

CALL ORDER: 650

PROJECT NO.: M60033 
District 6 Erosion Control – Various Counties

CONTRACTOR     TOTAL
B A B Inc 449,900
Kirk Barnes Construction 587,262

CALL ORDER: 655

PROJECT NO.: M60034 
District 6 Grading – Various  Counties

CONTRACTOR     TOTAL
Kirk Barnes Construction 779,750
Van Kirk Sand & Gravel 953,050

CALL ORDER: 750

PROJECT NO.: M70033 
District 7 Erosion Control – Various Counties

CONTRACTOR     TOTAL
B A B  Inc 367,350
Kirk Barnes Construction

CALL ORDER: 755

PROJECT NO.: M70034 
District 7 Grading – Various Counties

CONTRACTOR     TOTAL
Kirk Barnes Construction
Van Kirk Sand & Gravel 718,000

CALL ORDER: 850

PROJECT NO.: M80033 
District 8 Erosion Control – Various Counties

CONTRACTOR     TOTAL
Kirk Barnes Construction 312,000
Gross Seed Company 200,625

CALL ORDER: 855

PROJECT NO.: M80034
District 8 Grading – Various  Counties

CONTRACTOR     TOTAL
Kirk Barnes Construction 425,425
Van Kirk Sand & Gravel

 

Comments are closed.