CALL ORDER: 100
PROJECT NO.: NH-80-9(73)
Cass County
| CONTRACTORS | TOTAL |
| DIAMOND SURFACE INC | 1,474,675.32 |
| INTERSTATE SEALANT & CONCRETE INC. | 1,530,384.60 |
| IOWA CIVIL CONTRACTING INC. | 1,838,296.78 |
| SCODELLER CONSTRUCTION INC. |
CALL ORDER: 200
PROJECT NO.: NH-6-7(183)
Sarpy county
| CONTRACTOR | TOTAL |
| K2 REAL ESTATE DEVELOPMENT | 375,639.60 |
| KIEWIT INFRASTRUCTURE CO | |
| OMNI ENGINEERING (OLDCASTLE) | |
| SWAIN CONSTRUCTION INC. |
CALL ORDER: 205 (Tied with 210)
PROJECT NO.: NH-480-9(6), I-480, Dewey – 20th St.
Douglas County
| CONTRACTOR | TOTAL |
| DIAMOND SURFACE INC | 670,263.46 |
| DYKHUIS DRILLING CORP | 672,137.70 |
| INTERSTATE SEALANT & CONCRETE INC. | 649,956.30 |
| IOWA CIVIL CONTRACTING INC. | 696,263.86 |
| MIDWEST COATINGS CO INC | |
| SCODELLER CONSTRUCTION INC. | 1,361,220.84 |
CALL ORDER: 210 (Tied with 205)
PROJECT NO.: NH-480-9(6), I-80, 13th St-Iowa Line
Douglas County
| CONTRACTOR | TOTAL |
| DIAMOND SURFACE INC | 301,309.50 |
| DYKHUIS DRILLING CORP | 475,784.50 |
| INTERSTATE SEALANT & CONCRETE INC. | 337,706.30 |
| IOWA CIVIL CONTRACTING INC. | 330,753.90 |
| MIDWEST COATINGS CO INC | |
| SCODELLER CONSTRUCTION INC. | 715,440.00 |
CALL ORDER: 215
PROJECT NO.: MISC-6-7(1063)
Douglas County
| CONTRACTOR | TOTAL |
| CRAMER & ASSOCIATES INC | 149,251.00 |
| GARCIA-CHICOINE ENT. INC | |
| IOWA CIVIL CONTRACTING INC | 189,695.00 |
| JMN CONSTRUCTION | 462,275.00 |
| MCGILL RESTORATION INC | 197,373.00 |
| M. E. COLLINS CONTRACTING CO INC | 406,623.60 |
CALL ORDER: 220
PROJECT NO.: STP-91-6(113) N-91
Dodge County
| CONTRACTOR | TOTAL |
| CONSTRUCTORS INC | 5,393,183.09 |
| KNIFE RIVER MIDWEST | 5,769,574.27 |
| WESTERN ENGINEERING CO INC. | 5,548,775.17 |
CALL ORDER: 225
PROJECT NO.: NH-680-9(33)
Douglas County
| CONTRACTORS | TOTAL |
| GARCIA-CHICOINE ENT INC. | |
| IOWA CIVIL CONTRACTING INC | |
| MCGILL RESTORATION INC | 8,380,582.73 |
CALL ORDER: 230
PROJECT NO.: NH-30-7(121)
Washington County
| CONTRACTOR | TOTAL |
| K2 REAL ESTATE DEVELOPMENT | 448,486.10 |
| KIEWIT INFRASTRUCTURE | |
| M. E. COLLINS CONTRACTING CO | 419,620.19 |
| SWAIN CONSTRUCTION INC. |
CALL ORDER: 300
PROJECT NO.: NH-20-5(112)
Pierce & Cedar Counties
| CONTRACTOR | TOTAL |
| CONSTRUCTORS INC | 16,310,980.07 |
| KNIFE RIVER MIDWEST | 17,883,659.71 |
| WERNER CONSTRUCTION CO | 17,181,189.50 |
CALL ORDER: 305
PROJECT NO.: STP-57-4(116) N-57
Cedar County
| CONTRACTOR | TOTAL |
| CONSTRUCTORS INC | 5,374,013.25 |
| KNIFE RIVER MIDWEST | 5,343,095.18 |
| WERNER CONSTRUCTION CO | 5,123,607.26 |
CALL ORDER: 500
PROJECT NO.: MISC-D5(1006)
Multiple Counties
| CONTRACTOR | TOTAL |
| KIRK BARNES CONSTRUCTION | 205,655.00 |
| PAUL REED CONSTRUCTION & SUPPLY | 298,852.89 |
| TI-ZACK CONCRETE INC | 313,601.00 |
| VAN KIRK SAND & GRAVEL INC | 259,985.00 |
CALL ORDER:505
PROJECT NO.: MISC-D5(1007)
Multiple Counties
| CONTRACTOR | TOTAL |
| KIRK BARNES CONSTRUCTION | 367,943.00 |
| PAUL REED CONSTRUCTION & SUPPLY | 529,077.10 |
| TI-ZACK CONCRETE INC | 537,369.00 |
| VAN KIRK SAND & GRAVEL INC | 376,341.00 |
CALL ORDER: 515
PROJECT NO.: NH-80-2(111)
Cheyenne County
| DIAMOND SURFACE INC | 792,735.50 |
| DYKHUIS DRILLING CORP | 903,641.00 |
| IOWA CIVIL CONTRACTING INC | 1,105,044.42 |
| INTERSTATE SEALANT & CONCRETE INC | 823,995.10 |
| MIDWEST COATINGS CO INC | 940,587.74 |
| SCODELLER CONSTRUCTION INC | 1,346,098.00 |
CALL ORDER: 600
PROJECT NO.: NH-80-4(149)
Lincoln County
| CONTRACTORS | TOTAL |
| INTERSTATE SEALANT & CONCRETE INC | 329,890.00 |
| MIDWEST COATINGS CO INC | 255,850.00 |
| SCODELLER CONSTRUCTION | 314,400.00 |
CALL ORDER:605
PROJECT NO.: NH-80-3(161)
Lincoln County
| CONTRACTOR | TOTAL |
| INTERSTATE SEALANT & CONCRETE INC | 219,470.00 |
| MIDWEST COATINGS CO INC | 154,570.00 |
| SCODELLER CONSTRUCTION | 170,770.00 |
CALL ORDER: 615
PROJECT NO.: NH-80-4(152)
Pierce & Cedar Counties
| CONTRACTOR | TOTAL |
| INTERSTATE SEALANT & CONCRETE INC | |
| MIDWEST COATINGS CO INC | 346,160.00 |
| SCODELLER CONSTRUCTION | 416,970.00 |
CALL ORDER: 700
PROJECT NO.: MISC-D7(1006)
Perkins & Hitchcock Counties
| CONTRACTOR | TOTAL |
| BSB CONSTRUCTION INC | 346,445.10 |
| KIRK BARNES CONSTRUCTION INC | 282,961.00 |
| TI-ZACK CONCRETE INC | 392,614.00 |
| VAN KIRK SAND & GRAVEL |
CALL ORDER: 705
PROJECT NO.: STP-283-1(117)
Furnas & Gosper Counties
| CONTRACTOR | TOTAL |
| KIRK BARNES CONSTRUCTION | |
| PAULSEN INC | 5,266,059.28 |
| VONTZ PAVING | 6,152,105.35 |
| WERNER CONSTRUCTION CO | 5,883,278.95 |
| WESTERN ENGINEERING CO INC |
CALL ORDER: 710
PROJECT NO.:NH-6-3(127)
Furnas County
| CONTRACTOR | TOTAL |
| JJK CONSTRUCTION, LLC | 3,847,955.76 |
| KEA CONSTRUCTION, LLC | 3,728,260.56 |
| MIDWEST INFRASTRUCTURE INC | |
| PAULSEN INC | |
| SCUDDER BRIDGE CO (BRIDES INC) | 3,598,848.74 |
| SIMON CONTRACTORS INC | 4,259,000.00 |
| VONTZ PAVING |