June 20, 2019- Letting

Nebraska Department of Roads Bid Letting

Below are the UNOFFICIAL bid results for the Nebraska Department of Roads bid letting on June 20, 2019. 

CALL ORDER: 215

PROJECT NO.: STP-7(107)
CASS COUNTY

CONTRACTOR     TOTAL
CONSTRUCTORS, INC. 17,630,145.85 
GRAHAM GROUP 12,998,557.52
K2 REAL ESTATE DEVELOP  
SIMON CONTRACTORS  
HAWKINS CONSTRUCTION 16,790862.51 
A.M. COHRON & SON INC.
 
 

CALL ORDER: 300

PROJECT NO.: MISC-81-3(1057)
PLATTE COUNTY

CONTRACTOR     TOTAL
IOWA CIVIL CONTRACTING 3,088,193.63
VAN KIRK SAND & GRAVEL

CALL ORDER: 305

PROJECT NO.: STP-14-4(115)

KNOX COUNTY

CONTRACTOR     TOTAL
WERNER CONSTRUCTION 7,432,190.64
WESTERN ENGINEERING 8,245,717.79
KNIFE RIVER MIDWEST 7,809,888.41

CALL ORDER: 315

PROJECT NO.: STP-75-3(122)
BURT COUNTY

CONTRACTOR     TOTAL
WERNER CONSTRUCTION
WESTERN ENGINEERING
CONSTRUCTORS, INC. 7,974,119.13
K2 REAL ESTATE DEVELOP
KNIFE RIVER MIDWEST

CALL ORDER: 330

PROJECT NO.: STP-121-4(112)
CEDAR COUNTY

CONTRACTOR     TOTAL
GRAVES CONSTRUCTION
WESTERN ENGINEERING
KNIFE RIVER MIDWEST
DIXON CONSTRUCTION CO. 6,191,301.33
CHRISTENSEN BROS, INC.

CALL ORDER: 400

PROJECT NO.: STP-10-2(122)
BUFFALO COUNTY

CONTRACTOR     TOTAL
WERNER CONSTRUCTION 7,775,200.42
WESTERN ENGINEERING 9,847,999.25
PAULSEN, INC 8,192,064.50
VONTZ PAVING, INC 7,857,373.12
KNIFE RIVER MIDWEST
KEA CONSTRUCTORS LLC