CALL ORDER: 200
PROJECT NO.: NH-80-9(113)
CONTRACTORS | TOTAL |
HAWKINS CONSTRUCTION COMPANY | 16,353,434.26 |
IOWA CIVIL CONTRACTING INC | 13,987,892.65 |
CALL ORDER: 305
PROJECT NO.: S-275-6(1054)
CONTRACTOR | TOTAL |
GRAHAM CONSTRUCTION INC | 43,670,467.30 |
KOSS CONSTRUCTION CO | 37,772,493.01 |
WERNER CONSTRUCTORS – JV | 39,080,829.02 |
CALL ORDER: 310
PROJECT NO.: S-275-6(1055)
CONTRACTOR | TOTAL |
CEDAR VALLEY PAVING, LLC | |
GRAHAM CONSTRUCTION INC | 22,763,033.95 |
KOSS CONSTRUCTION CO | 18,546,966.46 |
WERNER CONSTRUCTORS – JV | 20,292,138.35 |
CALL ORDER: 315
PROJECT NO.: S-275-6(1056)
CONTRACTOR | TOTAL |
CEDAR VALLEY PAVING, LLC | |
GRAHAM CONSTRUCTION INC | 31,965,289.24 |
KOSS CONSTRUCTION CO | 26,894,819.51 |
WERNER CONSTRUCTORS – JV | 30,116,036.03 |
CALL ORDER: 320
PROJECT NO.: S-275-6(1057)
CONTRACTOR | TOTAL |
BLADE MASTERS GROUNDS MAINT. | 749,357.44 |
COMM. CONTRACTORS EQUIPMENT | |
HIGH PLAINS DIVERSIFIED | |
ME COLLINS CONTRACTING CO | 955,436.00 |
MOYNA & SONS LLC | 1,197,149.75 |
PRUSS EXCAVATION CO | 989,063.80 |
SAWYER CONSTRUCTION CO | |
VAN KIRK SAND & GRAVEL INC. |
CALL ORDER: 325
PROJECT NO.: S-275-6(1059)
CONTRACTOR | TOTAL |
BLADE MASTERS GROUNDS MAINT. | 1,357,901.70 |
COMM. CONTRACTORS EQUIPMENT | |
HIGH PLAINS DIVERSIFIED | |
ME COLLINS CONTRACTING CO | 1,883,833.92 |
MOYNA & SONS LLC | 2,006,897.45 |
PRUSS EXCAVATION CO | 1,929,794.40 |
SAWYER CONSTRUCTION CO | |
VAN KIRK SAND & GRAVEL INC. |
CALL ORDER: 550
PROJECT NO.: M50036
CONTRACTOR | TOTAL |
NO BIDS |
CALL ORDER: 555
PROJECT NO.: M50035
CONTRACTOR | TOTAL |
REED CONST & SUPPLY INC | 554,994.18 |
VAN KIRK SAND & GRAVEL INC |
CALL ORDER: 850
PROJECT NO.: M80036
CONTRACTOR | TOTAL |
NO BIDS |
CALL ORDER: 855
PROJECT NO.: M80035
CONTRACTOR | TOTAL |
VAN KIRK SAND & GRAVEL INC | 583,025.00 |