November 20, 2025 Letting
November 20, 2025 | Lettings
CALL ORDER: 100
PROJECT NO.:NH-92-6(123)
WAHOO WEST
| CONTRACTORS |
TOTAL |
| WERNER CONSTRUCTION INC |
$9,034,165.61 |
| CONSTRUCTORS INC |
$9,044,624.21 |
| KNIFE RIVER MIDWEST LLC |
$9,547,649.56 |
| WESTERN ENGINEERING COMPANY |
$9,694,717.32 |
| |
|
CALL ORDER: 200
PROJECT NO.: NH-80-9(142)
OMAHA
| CONTRACTORS |
TOTAL |
| OLD CASTLE/ OMNI ENGINEERING |
$1,056,872.41 |
| HAWKINS CONSTRUCTION COMPANY |
$1,314,969.37 |
| CONSTRUCTIORS INC |
$1,345,882.54 |
| WESTERN ENGINEERING COMPANY |
$1,371,301.80 |
| |
|
CALL ORDER: 400
PROJECT NO.: S-6-4(1022)
HASTINGS SOUTHEAST
| CONTRACTORS |
TOTAL |
| WERNER CONSTRUCTION INC |
$21,410,974.75 |
| PAULSEN INC |
$21,689,050.00 |
| WW CLYDE & CO |
$28,194,647.00 |
| |
|
CALL ORDER: 600
PROJECT NO.:NH-2-3(129)
BROKEN BOW – BERWYN
| CONTRACTORS |
TOTAL |
| PAULSEN INC |
$8,269,547.01 |
| WESTERN ENGINEERING COMPANY |
$8,679,148.44 |
| VONTZ PAVING INC |
$8,863,212.29 |
| CONSTRUCTORS INC |
$8,915,509.44 |
| WERNER CONSTRUCTION INC |
$9,130,648.35 |
| |
|
CALL ORDER: 700
PROJECT NO.:NH-6-3(132)
HOLBROOK – ARAPAHOE EAST
| CONTRACTORS |
TOTAL |
| VONTZ PAVING INC |
$8,037,250.67 |
| WERNER CONSTRUCTION INC |
$8,265,225.27 |
| PAULSEN INC |
$8,319,585.67 |
| |
|