CALL ORDER: 100
PROJECT NO.:ENH-49(46)
TECUMSEH HISTORIC SQUARE PRESERVATION
| CONTRACTORS | TOTAL |
| K2 REALESTATE DEVEVOPMENT LLC | $11,341,735.40 |
| CONSTRUCTORS INC | $14,899,183.12 |
| PAULSEN INC | $14,998,967.00 |
CALL ORDER: 105
PROJECT NO.: STP-TAP-4-6(117)
BEATRICE WEST BRIDGES
| CONTRACTORS | TOTAL |
| IOWA CIVIL CONTRACTING INC | $3,899,606.14 |
| JJK CONSTRUCTION LLC | $4,167,656.78 |
| KEA CONSTRUCTORS LLC | $4,187,305.56 |
| JMN CONSTRUCTION LLC | $4,188,085.62 |
| LOBATO CONSTRUCTION LLC | $4,344,868.43 |
| A.M. COHRON & SON INC | $4,364,422.96 |
| GENERAL EXCAVATING LLC | $4,581,266.55 |
| CONSTRUCTORS INC | $4,599,695.80 |
| UNITED CONTRACTORS INC | $4,704,493.13 |
| K2 REAL ESTATE DEVELOPMENT LLC | $4,900,417.28 |
| HERBST CONSTRUCTION INC | $5,091,830.00 |
| MIDWEST INFRASTRUCTURE INC | $5,191,951.55 |
CALL ORDER: 200
PROJECT NO.: STP-275-7(210)
DISTRICT A2-A HIGH MAST TOWER REPLACEMENT
| CONTRACTORS | TOTAL |
| SADLER ELECTRIC INC | $2,126,818.40 |
| WATTS ELECTRIC COMPANY | $2,242,457.96 |
| VALLEY CORPORATION | $2,373,555.70 |
CALL ORDER: 210
PROJECT NO.:MISC-80-9(1223)
I-80 DRAINAGE AT 96TH STREET
| CONTRACTORS | TOTAL |
| Project Withdrawn | |
CALL ORDER: 300
PROJECT NO.:MISC-12-5(1019)
N-12 NIOBRARA E & W WETLAND BANK
| CONTRACTORS | TOTAL |
| A&R CONSTRUCTION CO | $1,792,610.74 |
| W. THEISEN GRADING & EQUIPMENT | $2,357,562.63 |
| PRUSS EXCAVATION CO | $2,989,279.44 |
| AMES CONSTRUCTION INC | $3,536,850.00 |
| MYERS CONSTRUCTION INC | $5,846,862.60 |
CALL ORDER: 305
PROJECT NO.: TIB-275-6(150)
CUMING COUNTY
| CONTRACTORS | TOTAL |
| COMMONWEALTH ELECTRIC CO | $496,603.81 |
| WATTS ELECTRIC COMPANY | $530,072.78 |
| IES COMMERCIAL INC | $893,577.00 |
CALL ORDER: 400
PROJECT NO.: NH-81-2(144)
McCOOL, JUNCTION – YORK
| CONTRACTORS | TOTAL |
| WERNER CONMSTRUCTION INC | $10,393,093.34 |
| CONSTRUCTORS INC | $11,382,162.75 |
| WESTERN ENGINEERING COMPANY | $11,859,263.90 |
| VONTZ PAVING INC | $11,859,263.90 |
CALL ORDER: 500
PROJECT NO.:ITS-NH-D5(107)
DISTRICT 5 SIDEMOUNT DMS BOARDS
| CONTRACTORS | TOTAL |
| WATTS ELECTRIC COMPANY | $3,364,860.46 |
CALL ORDER: 505
PROJECT NO.:STP-80-1(207)
I-80 DISTRICT5 HIGH MAST TOWER REPLACEMENT
| CONTRACTORS | TOTAL |
| WATTS ELECTRIC COMPANY | $1,421,224.53 |
CALL ORDER: 600
PROJECT NO.: STP-FL-S86B(102)
S-86B HALSEY SPUR BRIDGE
| CONTRACTORS | TOTAL |
| MIDWEST INFRASTRUCTURE INC | $2,466,320.85 |
| KEA CONSTRUCTORS LLC | $2,469,251.75 |
| UNITED CONTRACTORS INC | $2,529,379.52 |
| SIMON CONTRACTORS | $2,587,000.00 |
| K2 REAL ESTATE DEVELOPMENT LLC | $2,685,973.82 |