CALL ORDER: 100
PROJECT NO.:NH-80-8(163)
SEWARD COUNTY
| CONTRACTORS |
TOTAL |
| MUTH ELECTRIC, INC |
|
| WATTS ELECTRIC COMPANY |
$985,587.17 |
| SADLER ELECTRIC |
$1,092,060.00 |
| |
|
CALL ORDER: 105
PROJECT NO.:STP-50-1(117)
PAWNEE COUNTY
| CONTRACTOR |
TOTAL |
| CONSTRUCTORS, INC |
$17,151,451.59 |
| GENERAL EXCAVATING LLC |
$15,247,326.77 |
| HAWKINS CONSTRUCTION COMPANY |
$14,120,446.10 |
| K2 REAL ESTATE DEVELOPMENT LLC |
|
| SCUDDER BRIDGE CO |
|
| |
|
CALL ORDER: 200
PROJECT NO.:ER-3840(13)
WASHINGTON COUNTY
| CONTRACTOR |
TOTAL |
| OMNI ENGINEERING (OLD CASTLE) |
$758,975.58 |
| WESTERN ENGINEERING CO INC |
$819,791.96 |
| |
|
CALL ORDER: 805
PROJECT NO.: NH-STP-20-4(128)
MULTIPLE COUNTIES
| CONTRACTOR |
TOTAL |
| MISSOURI PETROLEUM PRODUCTS CO |
$3,028,024.71 |
| STA-BILT CONSTRUCTION COMPANY |
$3,679,692.57 |