CALL ORDER: 105
PROJECT NO.: HISP-5231(14)
Lancaster County
CONTRACTORS | TOTAL |
COMMONWEALTH ELECTRIC CO | $1,987,898.00 |
WATTS ELECTRIC COMPANY | $2,501,879.65 |
CALL ORDER: 200
PROJECT NO.: STP-50-2(136)
Sarpy County
CONTRACTOR | TOTAL |
VRANA & SON CONSTRUCTION CO | $1,790,452.70 |
IOWA CIVIL CONTRACTING INC | |
GRAHAM CONSTRUCTION, INC | $1,452,010.70 |
K2 REAL ESTATE DEVELOPMENT | $1,850,301.38 |
RPL UTILITY LLC | $2,316,594.91 |
CALL ORDER: 300
PROJECT NO.: S-275-6(1053)
Dodge County
CONTRACTOR | TOTAL |
HAWKINS CONSTRUCTION COMPANY | $60,662,470.42 |
AMES CONSTRUCTION, INC | $62,428,504.55 |
MOYNA & SONS, LLC | $65,022,633.34 |
GRAHAM CONSTRUCTION, INC | $58,148,777.00 |
KOSS CONSTRUCTION | $61,707,038.98 |
CEDAR VALLEY PAVING, LLC | |
CONSTRUCTORS | $67,859,819.08 |
CALL ORDER: 310
PROJECT NO.: ER-2605(5)
Antelope County
CONTRACTOR | TOTAL |
A & R CONSTRUCTION | $209,299.99 |
RUTJENS CONSTRUCTION, INC | $212,308.00 |
VAN KIRK SAND & GRAVEL, INC | |
CALL ORDER: 315
PROJECT NO.: ER-2580(3)
Antelope County
CONTRACTOR | TOTAL |
A & R CONSTRUCTION CO | $199,110.64 |
HERBST CONSTRUCTION, INC | $189,020.00 |
RUTJENS CONSTRUCTION, INC | $195,423.00 |
VAN KIRK SAND & GRAVEL, INC | |
CALL ORDER: 400
PROJECT NO.: STP-S01D(103)
Adams County
CONTRACTOR | TOTAL |
VONTZ PAVING | $1,771,459.73 |
WERNER CONSTRUCTION INC | $1,732,967.16 |
CALL ORDER: 405
PROJECT NO.: NH-81-1(125)
Fillmore County
CONTRACTORS | TOTAL |
VONTZ PAVING | $3,239,906.79 |
WERNER CONSTRUCTION INC | $2,624,971.09 |
WESTERN ENGINEERING CO INC | $3,184,003.34 |
CALL ORDER: 505
PROJECT NO.: STP-385-2(113)
Deuel County
CONTRACTOR | TOTAL |
SIMON CONTRACTORS INC | |
WESTERN ENGINEERING CO, INC | $3,768,635.00 |
WERNER CONSTRUCTION INC | $3,421,442.95 |
CALL ORDER: 510
PROJECT NO.:STP-27-3(102)
Garden County
CONTRACTOR | TOTAL |
PAULSEN INC | $4,066,619.98 |
SIMON CONTRACTORS INC | |
WERNER CONSTRUCTION INC | $3,852,142.28 |
WESTERN ENGINEERING CO INC | $3,997,659.42 |
CALL ORDER: 610
PROJECT NO.: ITS-NH-D6(109)
Multiple Counties
CONTRACTOR | TOTAL |
WATTS ELECTRIC COMPANY | $5,929,704.15 |
CALL ORDER: 615
PROJECT NO.: ITS-NH-STP-D6(108)
Districtwide
CONTRACTOR | TOTAL |
IES COMMERCIAL INC | |
WATTS ELECTRIC COMPANY | $878,419.90 |
CALL ORDER:620
PROJECT NO.: STP-NH-61-2(115), STP-61-2(116)
Keith County
CONTRACTOR | TOTAL |
IOWA CIVIL CONTRACTING INC | |
PAULSEN INC | $6,799,698.03 |
WERNER CONSTRUCTION INC | |
WESTERN ENGINEERING CO INC | |
CALL ORDER: 700
PROJECT NO.: STP-17-1(108)
Hitchcock County
CONTRACTORS | TOTAL |
PAULSEN INC | $7,732,928.71 |
WERNER CONSTRUCTION LLC | $7,796,593.90 |
CALL ORDER: 705
PROJECT NO.: STP-S15A(101)
Chase County
CONTRACTORS | TOTAL |
PAULSEN INC | $4,405,033.54 |
WERNER CONSTRUCTION LLC | $4,057,834.59 |
CALL ORDER: 710
PROJECT NO.: STP-61-1(111)
Dundy County
CONTRACTOR | TOTAL |
PAULSEN INC | $2,698,785.75 |
WERNER CONSTRUCTION LLC | $2,626,070.22 |
CALL ORDER: 800
PROJECT NO.: STP-7-4(118)
Multiple Counties
CONTRACTOR | TOTAL |
KNIFE RIVER MIDWEST | $4,458,834.11 |
PAULSEN INC | |
WERNER CONSTRUCTION INC | $3,958,374.30 |
WESTERN ENGINEERING CO INC | $3,884,554.20 |
CALL ORDER: 805
PROJECT NO.:STP-183-4(118)
Rock County
CONTRACTOR | TOTAL |
KNIFE RIVER MIDWEST | $4,354,078.93 |
PAULSEN INC | |
WESTERN ENGINEERING CO INC | $3,980,254.49 |
WERNER CONSTRUCTION | $3,942,059.97 |
CALL ORDER: 810
PROJECT NO.: ER-8(28)
Furnas & Gosper Counties
CONTRACTOR | TOTAL |
WERNER CONSTRUCTION | $147,733.40 |
CALL ORDER: 815
PROJECT NO.: NH-20-3(113)
Brown County
CONTRACTOR | TOTAL |
A & R CONSTRUCTION CO | $8,722,621.39 |
BX CIVIL & CONSTRUCTION INC | $9,945,000.00 |
IOWA CIVIL CONTRACTING INC | $9,899,167.83 |