PROJECT NO.: MISC-34-6(1039)
Seward County
CONTRACTOR | TOTAL |
GARCIA-CHICOINE ENTR. INC. | |
K2 REAL ESTATE DEVEL. | $528,376.00 |
M.E. COLLINS CONTRACTING | |
NEUVIRTH CONSTRUCTION INC. | |
VAN KIRK SAND & GRAVEL INC. | $400,306.90 |
CALL ORDER: 210
PROJECT NO.: NH-480-9(3) POSTPONED TO JANUARY 28
Douglas County
CONTRACTOR | TOTAL |
CALL ORDER: 215
PROJECT NO.: NH-480-9(9) POSTPONED TO JANUARY 28
Douglas County
CONTRACTOR | TOTAL |
CALL ORDER: 220
PROJECT NO.: NH-75-2(185) POSTPONED TO JANUARY 28
Douglas County
CONTRACTOR | TOTAL |
CALL ORDER: 305
PROJECT NO.: STP-13-4(112) Pierce County
CONTRACTOR | TOTAL |
CONSTRUCTORS INC. | $1,828,596.23 |
KNIFE RIVER MIDWEST | $2,071,052.15 |
WERNER CONST. | $2,074,116.00 |
WESTERN ENGINEERING CO. | $1,920,248.30 |
CALL ORDER: 400
PROJECT NO.: STP-6-5(115)
Fillmore County
CONTRACTOR | TOTAL |
PAVERS COMPANIES | |
VAN KIRK SAND & GRAVEL INC. | $883,690.06 |
WERNER CONST. | $752,607.87 |
CALL ORDER: 500
PROJECT NO.: ITS-MISC-D5(1010)
Deuel, Kimball & Cheyenne Counties
CONTRACTOR | TOTAL |
CASPER ELECTRIC INC. | $3,838,084.84 |
WATTS ELECTRIC COMPANY | $2,929,790.88 |
CALL ORDER: 600
PROJECT NO.: STP-70-3(108)
Valley & Custer Counties
CONTRACTOR | TOTAL |
PAULSEN, INC. | $4,671,362.40 |
VONTZ PAVING, INC. | $4,132,888.77 |
WERNER CONST. | $4,425,639.94 |
WESTERN ENGINEERING CO | $4,140,855.34 |